Berliner, Morbio Inferiore
Excavation for the construction of a residential/commercial complex in the municipality of Morbio Inferiore. The excavation walls were supported by micropiles with strand tie-rods. The provisional excavation system allowed the recovery of the thrusts of the excavation and therefore the detensioning of the tie-rods during the execution of the construction in order to maximize the available commercial surface by building close to the berm with unilateral formwork.
Construction Site Duration: 2018
Amount of works: -
Company: EVLS SA
Work Direction: EVLS SA